Date |
Nate Golick |
Kevin Jaris |
|
Week 1 |
1/29/2013 |
Aquire additional motor |
Simulate power electronics |
Week 2 |
2/5/2013 |
Design pedal displacement system |
Contruct power electronics |
Week 3 |
2/12/2013 |
Create Simulink model of motor |
Create voltage profile |
Week 4 |
2/19/2013 |
Test power electronics with additional
motor |
|
Week 5 |
2/26/2013 |
Test power electronics with additional
motor |
|
Week 6 |
3/5/2013 |
Remove go kart motor from MUEV |
Create Simulink model of regenerative
braking |
Week 7 |
3/12/2013 |
Mount both motors onto test platform |
|
Week 8 |
3/26/2013 |
Test regenerative braking system |
|
Week 9 |
4/2/2013 |
Test regenerative braking system |
|
Week 10 |
4/9/2013 |
Test regenerative braking system |
|
Week 11 |
4/16/2013 |
Mount regenerative braking system to MUEV |
|
Week 12 |
4/23/2013 |
Test regenerative braking system on MUEV
|
|
Week 13 |
4/30/2013 |
Test regenerative braking system on MUEV
|
|
Week 14 |
5/7/2013 |
Finalize report and presentation |
|
Week 15 |
5/14/2013 |
Presentation |