Schedule of Events
Below are some important upcoming milestones for our senior project.
Important Milestones
- Order
Parts, December 13th, 2017
Orders for parts will be placed.
- Assemble PV and RF Subsystems,
February 1st, 2017
The two separate subsystems shall be built for testing.
- Assemble Full System, February 19th, 2017 The full system will be assembled and testing will begin.
- Collection of System Performance Data, March 5th, 2017 The performance of the system will be tested and data will be recorded and analyzed.
- Final Report, May 1st, 2017 The final report will be finished and submitted.
Presentations
- Student
Expo, April 12th, 2017
Bradley Univeristy's Renaissance Coliseum
- Final
Presentation,
May 1st, 2017 Bradley University's Marty Theater