Update Highlights

  • Overall System Update 100% - Finished testing and the verified operations of the SEL-2411 programmable automation controller.
  • Final Report Draft 30% - Adding equipment content to the report.
  • Slightly behind on the report but should be able to finish it by April 12 on time.
  • Will add content to the final presentation to be presented on April 21.

Detailed Schedule Update

Detailed Update April 6, 2016