Schedule Updates
April 6, 2016
Update Highlights
- Overall System Update 100% - Finished testing and the verified operations of the SEL-2411 programmable automation controller.
- Final Report Draft 30% - Adding equipment content to the report.
- Slightly behind on the report but should be able to finish it by April 12 on time.
- Will add content to the final presentation to be presented on April 21.
Detailed Schedule Update