AC System Monitoring Device

Schedule Updates

February 3, 2016

Update Highlights

  • Calculate Power Factor Build 80% - Built new capacitor bank for power factor correction. This did not fix the issue of the current harmonic distortion. In order to fix this issue we need to design a way to filter out the higher harmonics that in the system. Will need to extend the time needed to work on this part of the project.

Notes: Updates have been applied to the schedule accordingly with senior project changes. Design for the power factor correction will be more involved than anticipated due to the current harmonic distortion. This will set back other tasks later for the project. Senior project for spring of 2016 will continue work to the end of the semester instead of the March 24th.

Detailed Schedule Update

February 3, 2016 Detailed Schedule