Schedule Updates
November 4, 2015
Update Highlights
- Monitoring AC Voltage 90% - Adding voltage control with application of a Variac to test various input voltages; Successfully
connected high voltage probe for oscilloscope to the load to measure voltage; Will finialize AC voltage monitoring and start testing in the next week
- Monitoring AC Current 75% - RL load circuit built for the device current monitoring; Discovered that using transformer for inductive load is not
ideal; Using power reactor inductor to make more linear load; AC current monitoring should be finalized soon and should be able to start testing to continue to power
factor calculation build
- User interface Control 10% - Learning and implimenting controls for the user interfacing with the device
- Progress Presentation 0% - Planning on working on progress presentation in the next week to prepare for presenting in 2 weeks
Detailed Schedule Update