Project Timeline
Timeline for Spring 2008 - updated 5/07 - project completed
Lab Time |
Project Goal
|
January 23 – January 25
|
Re-establish virtual environment created in December |
January 28 – February 8
|
Complete graphics for sphere layers. (2 weeks) |
Mapping out position parameters, applying forces at specific ranges. | |
February 11 – February 22
|
Program plane layer over multiple surfaces. (2 weeks) |
February 25 – March 7
|
Complete graphics for multiple surfaces system (Part A-2 weeks) |
March 10 – March 14
|
Spring Break |
March 17 – March 21 |
Complete graphics for multiple surfaces system (Part B-1 week) |
March 24 – April 11
|
Integrate material properties into graphics model (3 weeks) |
April 14 – April 25
|
Integrate al three systems. Test haptic realism. (2 weeks) |
April 28 – May 2 |
Preparation for Oral Presentation and Final Project Report |
May 5 – May 9 | Final Project Report |
Timeline for Spring 2008 - updated 3/07
Lab Time |
Project Goal
|
January 23 – January 25
|
Re-establish virtual environment created in December |
January 28 – February 8
|
Complete graphics for sphere layers. (2 weeks) |
Mapping out position parameters, applying forces at specific ranges. | |
February 11 – February 22
|
Program plane layer over multiple surfaces. (2 weeks) |
February 25 – March 7
|
Complete graphics for multiple surfaces system (Part A-2 weeks) |
March 10 – March 14
|
Spring Break |
March 17 – March 21 |
Complete graphics for multiple surfaces system (Part B-1 week) |
March 24 – April 11
|
Integrate material properties into graphics model (3 weeks) |
April 14 – April 25
|
Integrate al three systems. Test haptic realism. (2 weeks) |
April 28 – May 2 |
Preparation for Oral Presentation and Final Project Report |
May 5 – May 9 | Final Project Report |
Timeline for Spring 2008 - updated 12/07
Lab Time |
Project Goal
|
January 23 – January 25
|
Re-establish virtual environment created in December |
January 28 – February 8
|
Complete graphics for sphere layers. (2 weeks) |
February 11 – February 22
|
Program plane layer over multiple surfaces. (2 weeks) |
February 25 – March 7
|
Complete graphics for multiple surfaces system (Part A-2 weeks) |
March 10 – March 14
|
Spring Break |
March 17 – March 21 |
Complete graphics for multiple surfaces system (Part B-1 week) |
March 24 – April 11
|
Integrate material properties into graphics model (3 weeks) |
April 14 – April 25
|
Integrate al three systems. Test haptic realism. (2 weeks) |
April 28 – May 2 |
Preparation for Oral Presentation and Final Project Report |
May 5 – May 9 | Final Project Report |